Loudoun and Prince William will see higher Electric Bills, NOVEC rate increase takes effect Nov. 1, adding about $13 a month
Customers of the Northern Virginia Electric Cooperative (NOVEC) in Loudoun and Prince William counties began paying more for electricity on Nov. 1, when the cooperative put a two-part rate increase into effect. NOVEC says an average residential member using 1,000 kilowatt-hours a month will see a bill rise from $145.29 to $158.64, an increase of $13.35.
What changed
According to NOVEC, the increase combines a change to its Power Cost Adjustment (PCA) with a separate increase in its distribution charge. The PCA, which appears on customer bills, rose by 1.16 cents per kilowatt-hour to $0.02482 per kWh. NOVEC says that adds about $11.62 a month for a household using 1,000 kWh. The distribution charge rose 5%, which accounts for the rest of the $13.35 total, according to Hoodline's report on the changes.
NOVEC says the PCA covers the cost of electricity it buys on the wholesale power market, along with the Halifax Biomass Electric Generation Facility, transmission costs, capacity and power purchase agreements. The cooperative says the adjustment also helps make up for higher costs it experienced during Winter Storm Fern earlier this year. As a not-for-profit cooperative, NOVEC says it passes the PCA charge on to members "without markup."
The distribution charge pays for delivering electricity to homes and businesses, including poles, wires, vegetation management and labor. NOVEC says distribution rates were last adjusted in 2023 and that consumer prices have risen by more than 2% a year since then, raising the cost of equipment, materials and contractors.
Why power costs are rising
NOVEC says the power market is experiencing rising demand while supply from new generation is not keeping pace, which has pushed up market prices for electricity. It also says utilities that buy power through PJM Interconnection, the regional grid operator, are facing higher costs from increased demand, retirements of existing generation, transmission investments, reliability requirements and higher wholesale prices.
Hoodline, citing Utility Dive, reported that PJM's total wholesale power cost rose 46% in the first seven months of 2026 compared with the same period of 2025, to $116.53 per megawatt-hour, and that PJM's independent market monitor attributed about 9% of wholesale prices through July directly to existing and forecast data center load. Hoodline also reported that PJM expects the zone covering Virginia to see the largest absolute increase in summer peak demand in the country between 2026 and 2030, largely because of data centers.
Data centers and who pays
NOVEC serves a region at the center of the data center industry. The cooperative says the number of data center accounts it serves has grown from 14 in 2015 to nearly 100. It says it assigns costs created by large customers to those customers, through separate rate classes, more frequent billing cycles and direct payment for dedicated infrastructure, and that it has assigned more than $1.7 billion in infrastructure costs to data centers. NOVEC says those costs are not shared with residential members.
At the same time, the cooperative acknowledges limits to that protection. "No electric utility can eliminate the effects of broader market conditions, including rising power supply and transmission costs," NOVEC says on its website.
The increase is the latest adjustment members have seen as demand from large customers grows. Members with questions about their own bills can find a detailed breakdown on NOVEC's PCA page.
Sources
- NOVEC: Maintaining Reliable Power While Managing Rising Costs (November 2026 rate changes)
- NOVEC: PCA – Power Cost Adjustment
- NOVEC: Future Ready
- Hoodline: NOVEC Hikes Rates Again, Adds $13 a Month as Data Centers Drain the Grid
Email the Board of Supervisors at:
Phyllis J. Randall (Chair, At-Large) – Phyllis.Randall@loudoun.gov,
Michael R. Turner (Vice Chair, Ashburn District) – Mike.Turner@loudoun.gov,
Juli E. Briskman (Algonkian District) – Juli.Briskman@loudoun.gov,
Sylvia R. Glass (Broad Run District) – Sylvia.Glass@loudoun.gov,
Caleb Kershner (Catoctin District) – caleb.kershner@loudoun.gov,
Matthew F. Letourneau (Dulles District) – Matt.Letourneau@loudoun.gov,
Kristen C. Umstattd (Leesburg District) – Kristen.Umstattd@loudoun.gov,
Laura A. TeKrony (Little River District) – Laura.TeKrony@loudoun.gov,
Koran Saines (Sterling District) – Koran.Saines@loudoun.gov
Loudoun County is a county in Northern Virginia. Its county seat is Leesburg.
Email the Prince William Board of Supervisors At:
Chair At-Large (Deshundra Jefferson) – djefferson@pwcgov.org,
Brentsville (Tom Gordy): tgordy@pwcgov.org,
Coles (Yesli Vega): yvega@pwcgov.org,
Gainesville (George Stewart): Gainesville@pwcgov.org,
Neabsco (Victor Angry): vsangry@pwcgov.org,
Occoquan (Kenny Boddye): kboddye@pwcgov.org,
Potomac (Andrea Bailey): abailey@pwcgov.org,
Woodbridge (Jeannie LaCroix): jlacroix@pwcgov.org,
General Board: bocs@pwcgov.org,
Prince William County is a county in Northern Virginia. Its county seat is Manassas, an independent city.
Loudoun County Prince William County Andrea Bailey Caleb Kershner Data Centers Deshundra Jefferson electric rates Jeannie LaCroix Juli Briskman Kenny Boddye Koran Saines Kristen Umstattd Laura TeKrony Loudoun County Loudoun County Board of Supervisors Matt Letourneau Mike Turner NOVEC Phyllis Randall Prince William prince william county Sylvia Glass Tom Gordy utility bills Victor Angry Yesli Vega
All Virginia News is published by ALL VIRGINIA NEWS, LLC. How we're funded · Corrections · Ethics