Virginia Running Short on Shovel-Ready Megasites as State Site Funding Falls

Originally published by Virginia Business

A large, freshly graded red-clay industrial site surrounded by Virginia woodland.

Virginia's recent string of major economic development wins has depleted its supply of large, construction-ready industrial sites, and state funding to replace them has declined steeply, according to a Virginia Business report.

Shovel-ready sites, where construction can begin within 12 to 18 months, take years and millions of dollars to develop. The Southern Virginia Megasite at Berry Hill, a 3,500-acre property in Pittsylvania County, illustrates the timeline. Danville and Pittsylvania bought the land in 2008, began site work in 2017 and, using more than $1.3 million from the state's Virginia Business Ready Sites Program (VBRSP) in 2022, built a 55-acre pad. Battery separator maker Microporous later announced a $1.35 billion facility there that is expected to bring 1,832 jobs.

"We would not have had that project if it hadn't had been for a pad," said Matt Rowe, Pittsylvania's economic development director. This year, Stack Infrastructure signed a performance agreement for a 2,990-acre data center campus at the site, committing to invest at least $73.5 billion and create at least 2,050 jobs. Rowe said the megasite's development took about $240 million in public and private investment.

The VBRSP, created in 2015, received roughly $1 million a year until 2021, when lawmakers allocated $5.5 million. Under Gov. Glenn Youngkin, funding rose to $109 million in fiscal 2023 and $125 million the next year. The Virginia Economic Development Partnership (VEDP), which administers the fund, says funded sites have directly generated more than 12,000 jobs and over $9.4 billion in capital investment since 2015. Between January 2015 and September 2022, Virginia won only one megaproject, Lego Group's $1 billion Chesterfield County plant.

Funding then fell to $40 million in fiscal 2025 and $30 million in fiscal 2026. The current biennial budget provides $30 million for fiscal 2027 and $20 million for fiscal 2028. VEDP President and CEO Jason El Koubi said the program, which requires local matches, sees five to 10 times more demand than it can meet, and that the state has "fewer resources today to replenish the supply of sites."

Greensville County's 1,560-acre Mid-Atlantic Advanced Manufacturing Center is currently the state's only shovel-ready, available property with at least 250 contiguous acres, according to the report. An 800-acre parcel there is under a purchase agreement for an unannounced project. "Virginia has put money into these site developments, and it's been great, but it is not enough," said Natalie Slate, Greensville's economic development director.

Gentry Locke Consulting President Greg Habeeb, a former state delegate, said site investment competes with immediate budget needs such as paying teachers and police. Lawmakers this year also set aside $725 million to offset federal cuts to Medicaid and other programs, and moved the $80.8 million balance of an unused megasite acquisition fund to the general fund.

Other states are spending more. Ohio, ranked first in CNBC's Top States for Business with Virginia third, dedicated $175 million to site readiness, and North Carolina's megasite fund received $97.9 million last year. "We're certainly not keeping up with other states," said Chris Lloyd of McGuireWoods Consulting, though he said he remains hopeful that characterizing the next round of sites could justify a return to higher funding.

Source: Virginia Business

Greensville County is a county in Southside Virginia. Its county seat is Emporia, an independent city.

Greensville County 2025 2026 2027 agreement allocated balance battery between Budget Business Business Ready Sites Program campus Capital Chesterfield Chesterfield County Chris construction County's current currently Danville Data Data Center delegate development directly economic development facility First fiscal five fund funding general general General Fund Glenn Youngkin Greensville County Immediate Infrastructure Investment Jobs keeping Land last year Lawmakers Lego Manufacturing Medicaid megasites Million money Moved needs next next year North officials Pittsylvania County Plant Police preparation President Private program programs project property provides Public readiness remains requires resources short spending state budget state funding states Teachers there timeline took VEDP Virginia Virginia Business Virginia economy Virginia's within work

All Virginia News is published by ALL VIRGINIA NEWS, LLC. How we're funded · Corrections · Ethics

2026-11-21 · 78196e8